Level:
Correct: 0
Incorrect: 0
Marks: 0/0
Exam Practice
Course:
Topics:
OCR GCSE Maths (Higher non-calculator) Smart practice A mixed round aimed at your weak spots
Unit 1
Number Operations and Integers
Unit 2
Fractions, Decimals and Percentages
Unit 3
Indices and Surds
Unit 4
Approximation and Estimation
Unit 5
Ratio, Proportion and Rates of Change
Unit 6
Algebra
Unit 7
Graphs of Equations and Functions
Unit 8
Basic Geometry
Unit 9
Congruence and Similarity
Unit 10
Mensuration
Unit 11
Probability
Unit 12
Statistics
Avg
score:
–
Topics
done:
0/121

Estimation

Practise 15 exam-style questions on Estimation for OCR GCSE Maths (Higher non-calculator). Write your answer as you would in the exam and get it marked in seconds against the mark scheme, point by point, with the Study Helper on hand if you get stuck.

  • 15 questions
  • 1–5 marks each
  • Instant marking
  • No sign-up needed
15 questions, marked as you go

Sample questions with model answers

Here are 4 of the questions in this topic, each with a model answer, an explanation of why it earns the marks and the mark scheme an examiner would use.

Question 1

1 mark

Harry writes,

\(3.9 \times 5.1 = 20\)

Explain why Harry should have used the symbol \(\approx\) instead of \(=\).

Model answer

20 is only an approximate answer: \(3.9 \times 5.1 \approx 4 \times 5 = 20\), but the exact answer is 19.89. The symbol \(\approx\) means 'is approximately equal to'.

Explanation

The symbol = means the two sides are exactly equal. Rounding 3.9 and 5.1 gives an estimate, so the correct symbol is \(\approx\), 'approximately equal to'. Using = for an estimate is a common error in working.

Mark scheme
  1. 1 mark

    B1 for: 20 is an estimate (approximation), not the exact answer

    Accept 'the exact answer is 19.89, not 20' or '\(3.9 \times 5.1\) is approximately 20' oe. Do not accept 'it is wrong' with no reference to approximation.

Question 2

2 marks

A car travels 238 miles in 3 hours 52 minutes.

Estimate the average speed of the car.

Model answer

238 miles \(\approx\) 240 miles
3 hours 52 minutes \(\approx\) 4 hours
Speed \(\approx 240 \div 4 = 60\) mph

Explanation

Average speed is distance divided by time. 3 hours 52 minutes is nearly 4 hours, and 238 is close to 240, which divides neatly by 4. The real speed is a little over 60 mph because the time was rounded up.

Mark scheme
  1. 1 mark

    M1 for \(240 \div 4\) oe

    Distance and time rounded sensibly, e.g. \(200 \div 4\) or \(240 \div 4\). Using 3.52 hours for 3 hours 52 minutes scores M0 unless rounded to 4.

  2. 1 mark

    A1 for 60 mph

    Accept answers from 50 to 62 from a correct method with sensible rounding (e.g. 50 from \(200 \div 4\)). Units not required.

Question 3

3 marks

Estimate the value of

\(\sqrt{\dfrac{38.7 \times 5.2}{2.05}}\)

Model answer

\(\sqrt{\dfrac{38.7 \times 5.2}{2.05}} \approx \sqrt{\dfrac{40 \times 5}{2}} = \sqrt{\dfrac{200}{2}} = \sqrt{100} = 10\)

Explanation

Round each number to 1 significant figure and work out the expression inside the square root first. Rounding has made it a square number, so the square root is easy. The exact value is about 9.9.

Mark scheme
  1. 1 mark

    M1 for at least two of 40, 5 and 2 used

  2. 1 mark

    M1 for \(\dfrac{40 \times 5}{2} = 100\)

    FT their rounded values.

  3. 1 mark

    A1 for 10

    From correct working. 100 (no square root) scores M2 A0.

Question 4

4 marks

A swimming pool is in the shape of a cuboid.
It is 24.6 m long, 9.8 m wide and 1.9 m deep.

It costs £1.96 for each m³ of water used to fill the pool.

By rounding each number to 1 significant figure, estimate the cost of filling the pool with water.

Model answer

\(24.6 \approx 20\), \(9.8 \approx 10\), \(1.9 \approx 2\), \(1.96 \approx 2\)
Volume \(\approx 20 \times 10 \times 2 = 400\) m³
Cost \(\approx 400 \times 2 = 800\)
The estimated cost is £800.

Explanation

The question says round each number to 1 significant figure, so 24.6 becomes 20 (not 25). The volume of a cuboid is length \(\times\) width \(\times\) depth, and the cost is the volume times the price per m³. The exact cost is about £898; rounding 24.6 down to 20 makes this estimate low.

Mark scheme
  1. 1 mark

    B1 for at least three of 20, 10, 2 and 2

    Each value rounded to 1 significant figure. 25 for 24.6 is 2 significant figures: B0 unless three others are correct.

  2. 1 mark

    M1 for \(20 \times 10 \times 2\) (= 400) oe

    FT their rounded values. Volume = length \(\times\) width \(\times\) depth.

  3. 1 mark

    M1 for their \(400 \times 2\)

    Multiplying their volume by their rounded cost.

  4. 1 mark

    A1 for £800

    cao, from correct rounding to 1 significant figure. (\(25 \times 10 \times 2 \times 2 = 1000\) scores B0 M1 M1 A0.)

Ready to try the rest? Every answer you write is marked against the mark scheme, so you can see exactly where the marks are.

Study Helper Hints first, answers after you try

Stuck on this one? Ask for a hint and I’ll point you in the right direction, without giving the answer away. Once you’ve checked your answer, I’ll show you how the marks are awarded.