Level:
Correct: 0
Incorrect: 0
Marks: 0/0
Exam Practice
Course:
Topics:
Edexcel GCSE Statistics (Higher Paper 2) Smart practice A mixed round aimed at your weak spots
Unit 1
The statistical enquiry cycle
Statistical enquiry cycle stages 1 and 2; (a) Planning: 1a.01, 1a.02, 1a.03
Statistical enquiry cycle: planning and collecting
Statistical enquiry cycle stages 3, 4 and 5
Statistical enquiry cycle: interpreting and evaluating
Unit 2
The collection of data
(b) Types of data: 1b.01, 1b.02, 1b.03
Types of data and variables
(b) Types of data: 1b.04; (d) Collecting data: 1d.01, 1d.02
Primary and secondary data, reliability and validity
(c) Population and sampling: 1c.01, 1c.02, 1c.03
Populations, sampling frames and non-random sampling
(c) Population and sampling: 1c.04, 1c.05
Random and systematic sampling
(c) Population and sampling: 1c.06
Stratified sampling
(d) Collecting data: 1d.05, 1d.06
Problems with collected data and cleaning data
Unit 3
Processing, representing and analysing data
(a) Tabulation, diagrams and representation: 2a.01
Tabulation, tallies, pictograms and two-way tables
(a) Tabulation, diagrams and representation: 2a.01, 2a.02
Pie charts and comparative pie charts
(a) Tabulation, diagrams and representation: 2a.01
Stem and leaf diagrams
(a) Tabulation, diagrams and representation: 2a.02
Population pyramids, choropleth maps and 2D and 3D diagrams
(a) Tabulation, diagrams and representation: 2a.04
Histograms and frequency density
(a) Tabulation, diagrams and representation: 2a.05, 2a.06, 2a.07, 2a.08
Choosing representations and misleading diagrams
(a) Tabulation, diagrams and representation: 2a.09, 2a.10
Skewness
(b) Measures of central tendency: 2b.01, 2b.02, 2b.03
Mode, median and mean
(b) Measures of central tendency: 2b.01
Weighted mean and geometric mean
(c) Measures of dispersion: 2c.01, 2c.06
Standard deviation and standardised scores
(a) Tabulation, diagrams and representation: 2a.03; (c) Measures of dispersion: 2c.02, 2c.03
Box plots and outliers
(b) Measures of central tendency: 2b.03; (c) Measures of dispersion: 2c.04, 2c.05
Comparing distributions
(d) Further summary statistics: 2d.01
Index numbers
(d) Further summary statistics: 2d.02
Rates of change
(e) Scatter diagrams and correlation: 2e.01, 2e.02, 2e.03
Scatter diagrams, correlation and causation
(e) Scatter diagrams and correlation: 2e.04
Lines of best fit and regression lines
(e) Scatter diagrams and correlation: 2e.05, 2e.06, 2e.07, 2e.08
Spearman's rank and product moment correlation coefficients
(f) Time series: 2f.01, 2f.02; (b) 2b.01 mean seasonal variation
Time series, moving averages and seasonal variation
(g) Quality assurance: 2g.01, 2g.02
Quality assurance and control charts
(h) Estimation: 2h.01, 2h.02, 2h.03
Estimation, sample size and capture-recapture
Unit 4
Probability
3. Probability: 3p.01, 3p.02, 3p.03, 3p.04
Probability, expected frequency and risk
3. Probability: 3p.05, 3p.06, 3p.10
Experimental and theoretical probability and bias
3. Probability: 3p.11
Binomial distribution
3. Probability: 3p.12, 3p.13
Normal distribution
Avg
score:
–
Topics
done:
0/40

Quality assurance and control charts

Practise 17 exam-style questions on Quality assurance and control charts for Edexcel GCSE Statistics (Higher Paper 2). Write your answer as you would in the exam and get it marked in seconds against the mark scheme, point by point, with the Study Helper on hand if you get stuck.

  • 17 questions
  • 1–5 marks each
  • Instant marking
  • No sign-up needed
17 questions, marked as you go

Sample questions with model answers

Here are 4 of the questions in this topic, each with a model answer, an explanation of why it earns the marks and the mark scheme an examiner would use.

Question 1

1 mark

A bakery checks the masses of its croissants. Every hour, a sample of 5 croissants is weighed. The bakery plots the median mass of each sample on a control chart, instead of the mean mass.

Give one advantage of using the sample median rather than the sample mean.

Model answer

The median is quicker to find: the 5 masses only need to be put in order and the middle one read off, with no calculation.

Explanation

Control charts can be kept for the sample mean, the sample median or the sample range. The median is quick to find on a production line and is not pulled up or down by one unusual item. Vague answers such as 'it is more accurate' earn no credit.

Mark scheme
  1. 1 mark

    B1 for a correct advantage, e.g. the median is quicker (easier) to find, as no calculation is needed: the 5 masses are put in order and the middle one is taken / the median is not affected by one unusually heavy or light croissant (an extreme value)

    oe. Accept 'it can be found without a calculator' or 'it is quicker to work out'. B0 for 'it is more accurate', 'it is more reliable' or 'it is better' with no reason. B0 for 'it shows how spread out the masses are' (that is what a chart for the sample ranges does). Ignore extraneous non-contradictory comments.

Question 2

2 marks

A machine cuts candles to a target length of 200 mm. Every hour, Ann measures a sample of 5 candles and plots the range of their lengths on a control chart.

Whenever a sample range was between the upper warning line and the upper action line, Ann took the next sample straight away.

The control chart shows the sample ranges for samples 1 to 12.

Ann says,
"The machine did not need to be stopped until after sample 11, because that was the first sample range above the upper action line."

Is Ann correct? Give a reason for your answer.

A graph of Sample range (mm) (vertical axis, 0 to 7, marked every 1) against Sample number (horizontal axis, 0 to 13, marked every 1), on a grid with 5 small squares to each large square. The line labelled "Upper action line" is a horizontal straight line crossing the y-axis at (0, 5.5) (the line y = 5.5). The line labelled "Upper warning line" is a horizontal straight line crossing the y-axis at (0, 4.2) (the line y = 4.2). The graph is made of straight-line sections joining (1, 2.2), (2, 1.6), (3, 2.8), (4, 4.6), (5, 2.4), (6, 3), (7, 2), (8, 4.4), (9, 4.8), (10, 3.6), (11, 5.8) and (12, 4). The line labelled "Upper action line" and the graph cross at 2 points, which can be read from the grid. The line labelled "Upper warning line" and the graph cross at 6 points, which can be read from the grid. A cross is marked at (1, 2.2). A cross is marked at (2, 1.6). A cross is marked at (3, 2.8). A cross is marked at (4, 4.6). A cross is marked at (5, 2.4). A cross is marked at (6, 3). A cross is marked at (7, 2). A cross is marked at (8, 4.4). A cross is marked at (9, 4.8). A cross is marked at (10, 3.6). A cross is marked at (11, 5.8). A cross is marked at (12, 4).

Model answer

No.
Sample 4 was between the upper warning line and the upper action line, so sample 5 was taken straight away. Sample 5 was below the warning line, so the machine could continue.
Sample 8 (about 4.4 mm) was between the lines, so sample 9 was taken straight away.
Sample 9 (about 4.8 mm) was also between the upper warning line and the upper action line: two samples in a row beyond the warning line.
So the machine should have been stopped after sample 9, before any range went above the action line.

Explanation

One sample range between the warning and action lines means take another sample at once; if that one is also beyond the warning line, the process is stopped and reset. So the machine should have been stopped after sample 9, before any range crossed the action line. Waiting for a point above the action line, as Ann did, lets inconsistent candles be made for longer.

Mark scheme
  1. 1 mark

    B1 for No, the machine should first have been stopped after sample 9

    Both the decision and sample 9 are needed. 'No' with sample 4 or sample 8 (a single range between the lines, after which another sample is taken) scores B0B0. 'Yes' scores B0B0.

  2. 1 mark

    B1 for the range for sample 9 is between the upper warning line and the upper action line, and so was the range for sample 8, the sample just before it (two samples in a row beyond the upper warning line)

    Dependent on the previous mark. The idea of two samples in a row (one straight after the other) beyond the upper warning line is needed. 'Sample 9 is above the warning line' alone scores B0. Readings, if given, should be about 4.4 mm for sample 8 and 4.8 mm for sample 9 (accept within 0.1 mm).

Question 3

3 marks

A machine makes buttons. Every hour, a sample of 5 buttons is measured and the median diameter of the sample is plotted on a control chart.

When the machine is working correctly, about 1 in 20 of the sample medians lie outside two of the lines on the chart. These two lines are at 14.6 mm and 15.4 mm.

Work out where the action lines should be drawn on the chart.

Model answer

About 1 in 20 sample medians lie outside the warning lines, so 14.6 mm and 15.4 mm are the warning lines.
Target \(= (14.6 + 15.4) \div 2 = 15.0\) mm
The warning lines are 2 s.d. from the target: \(2 \times \text{s.d.} = 0.4\), so s.d. = 0.2 mm
Action lines \(= 15.0 \pm 3 \times 0.2\) = 14.4 mm and 15.6 mm

Explanation

Lines with about 1 in 20 values outside them are the warning lines, 2 standard deviations from the target; almost no values lie outside the action lines, at 3 standard deviations. Halving the distance from the target to a warning line gives one standard deviation, and the action lines are 3 of these from the target.

Mark scheme
  1. 1 mark

    B1 for recognising that 14.6 mm and 15.4 mm are the warning lines, 2 standard deviations (of the sample medians) either side of the target of 15.0 mm

    May be implied by a correct method using 2 standard deviations, e.g. \((15.4 - 15.0) \div 2\). The target is halfway between the lines: \((14.6 + 15.4) \div 2 = 15.0\).

  2. 1 mark

    M1 for finding the standard deviation of the sample medians, e.g. \((15.4 - 14.6) \div 4\) (= 0.2) or \((15.4 - 15.0) \div 2\)

    Implied by 0.2. Using 0.4 or 0.8 as the standard deviation scores M0A0.

  3. 1 mark

    A1 for 14.4 (mm) and 15.6 (mm)

    cao. Both values needed, identified as the action lines. 14.2 and 15.8 (the gap from a warning line to an action line made the same as the gap from the target to a warning line) score A0. A correct answer with no working scores full marks.

Question 4

4 marks

A bakery makes bread rolls with a target mass of 68.0 g. Every 30 minutes, a sample of 5 rolls is weighed and the mean mass of the sample is plotted on a control chart.

When the process is working correctly, the sample means are modelled by the normal distribution \(\text{N}(68.0, 0.09)\).

The masses, in grams, of the rolls in the latest sample are

68.9   69.3   68.4   68.6   69.1

Priya says,
"Two of these rolls are above the upper action line, so the process must be stopped."

Is Priya correct? You must show your working.

Model answer

Standard deviation of the sample means \(= \sqrt{0.09} = 0.3\) g
Upper warning line \(= 68.0 + 2 \times 0.3 = 68.6\) g
Upper action line \(= 68.0 + 3 \times 0.3 = 68.9\) g
Sample mean \(= (68.9 + 69.3 + 68.4 + 68.6 + 69.1) \div 5 = 344.3 \div 5 = 68.86\) g
Priya is not correct. The lines are for sample means, not for single rolls. The sample mean, 68.86 g, is between the upper warning line (68.6 g) and the upper action line (68.9 g), so another sample should be taken straight away rather than stopping the process.

Explanation

The lines are 2 and 3 standard deviations of the sample means from the target, found from the variance in \(\text{N}(68.0, 0.09)\). Single rolls are more spread out than sample means, so rolls above the action line are expected now and then and are not compared with it. Here the sample mean is between the warning and action lines, which calls for another sample, not a stop.

Mark scheme
  1. 1 mark

    B1 for standard deviation of the sample means \(= \sqrt{0.09} = 0.3\) (g)

    May be implied by correct lines. In \(\text{N}(68.0, 0.09)\) the second number is the variance.

  2. 1 mark

    B1 for upper warning line 68.6 (g) and upper action line 68.9 (g)

    Both needed. Accept all four lines (lower warning line 67.4 g, lower action line 67.1 g as well). Lines found using 0.09 as the standard deviation (68.18 and 68.27) score B0.

  3. 1 mark

    M1 for the sample mean \((68.9 + 69.3 + 68.4 + 68.6 + 69.1) \div 5\) (= 68.86)

    Implied by 68.86.

  4. 1 mark

    B1 for No, with a correct reason: the lines are for sample means, not single rolls, and the sample mean (68.86 g) is between the upper warning line and the upper action line, so another sample should be taken straight away (the process should not be stopped yet)

    Dependent on M1. The decision, the comparison of the sample mean with the lines and the correct action are all needed. ft their lines provided their warning line is below their action line. Answer only scores 0.

Ready to try the rest? Every answer you write is marked against the mark scheme, so you can see exactly where the marks are.

Study Helper Hints first, answers after you try

Stuck on this one? Ask for a hint and I’ll point you in the right direction, without giving the answer away. Once you’ve checked your answer, I’ll show you how the marks are awarded.