A company uses a CNC lathe to make a batch of 2000 aluminium spacers. Each spacer must be 25.00 ± 0.05 mm long, with a hole of 8.00 ± 0.02 mm diameter through its centre.
Describe, in stages, the quality control checks that should be carried out, from the delivery of the aluminium bar to the dispatch of the finished spacers.
Model answer
1. When the aluminium bar arrives, check the material certificate to confirm the correct alloy, and measure the bar diameter with a micrometer to make sure it is the right stock size and undamaged.
2. Before the batch starts, check the CNC program and tool settings, then make one 'first-off' spacer. Measure its length with a micrometer and check the hole with an 8 mm go/no-go plug gauge. Only start the batch when this spacer is within tolerance.
3. During production, take every 50th spacer and check the length with a 25 mm go/no-go gap gauge and the hole with the plug gauge. Write the micrometer readings on a chart.
4. Watch the chart for sizes drifting towards a limit as the cutting tool wears, and adjust the tool offset or change the tool before any parts go out of tolerance.
5. If a sample fails, stop the lathe, quarantine all spacers made since the last good check and inspect them, scrapping any that are out of tolerance.
6. Check spacers visually for burrs and scratches as they are deburred.
7. Before dispatch, inspect a random sample of the finished batch, then label the boxes and keep the inspection records so the batch can be traced if a customer reports a problem.
Explanation
Top answers follow the product through the factory: checking incoming material, a first-off inspection, regular in-process sampling with named gauges, acting on trends and failures, and a final inspection with records. Each stage should say what is checked and with what. A list such as 'check the metal, measure the parts, inspect at the end' stays in Level 1.